#1642: TVOS Meeting January 28, 2010 Agenda
Submitted by Barb on Wed, 01/27/2010 - 09:09. For VisitorsFri, 01/28/2000 - 14:00
Meeting to be held at High Country Lodge
January 28, 2010
2PM
Black Diamond
Turner Valley Oilfield Society
A G E N D A
January 28, 2010
2:00 PM
High Country Lodge, Black Diamond
Meeting called to order
January 28, 2010
2PM
Black Diamond
Turner Valley Oilfield Society
A G E N D A
January 28, 2010
2:00 PM
High Country Lodge, Black Diamond
Meeting called to order
» calendar
#1641: Alberta Petroleum Discoveries 2010 History Calendar - Book
Submitted by Barb on Wed, 12/02/2009 - 14:04. For Visitors | Oil Fields#1627: Royalite (Dingman) #2 Operations Update September 8, 2009
Submitted by Barb on Wed, 09/09/2009 - 09:55. For Visitors- On August 31, the ERCB notified Lionhead Engineering that the downhole operations have been reviewed. The ERCB has indicated the well has been satisfactorily abandoned.
- On September 8, the well was tested for the presence of gas. No gas was detected in the well. Tests were also conducted to determine if any gas was seeping through the ground near the well head. No gas was detected. The tests were witnessed by representatives from the ERCB.
#1626: Turner Valley Oilfield Society Annual General Meeting
Submitted by Barb on Wed, 09/02/2009 - 09:03. For VisitorsThu, 09/24/2009 - 19:30
Turner Valley Oilfield Society
Annual General Meeting
September 24, 2009
Flare N Derrick
7:30 PM
A G E N D A
Meeting Called Turner to Order
Adoption of Agenda
Approval of Minutes from September 25, 2008
Annual General Meeting
September 24, 2009
Flare N Derrick
7:30 PM
A G E N D A
Meeting Called Turner to Order
Adoption of Agenda
Approval of Minutes from September 25, 2008
» calendar
#1625: Royalite (Dingman) #2 Operations Update August 17, 2009
Submitted by Barb on Wed, 08/19/2009 - 12:41. For Visitors- The well has been cleaned out to the planned casing set depth. Casing will be installed August 18 and cemented to surface.
- A caliper log indicated multiple sections of old casing are in the well. This resulted in the difficulty of cleaning out the well.
#1624: Royalite (Dingman) #2 Operations Update August 14-16, 2009
Submitted by Barb on Mon, 08/17/2009 - 08:02. For Visitors- continued to clean out well in preparation of logging and setting casing. Continue to get shale and pieces of metal circulated back to surface
- the seepage area gas has declined to no measurable flow at this time. The area continues to be monitored.
#1623: Royalite (Dingman) #2 Operations Update August 13, 2009
Submitted by Barb on Fri, 08/14/2009 - 11:10. For Visitors- Continue to clean out well bore prior to running and cementing casing.
- Pieces of metal and shale are being cleaned out of the well.
- The seepage area gas has declined to no measurabel flow at this time. The area continues to be monitored.
#1622: Royalite (Dingman) #2 Operations Update August 12, 2009
Submitted by Barb on Thu, 08/13/2009 - 07:41. For Visitors- Removed drill pipe from the well. Attempted to log but could not get tools below 205 meter
- Re-run drill pipe to clean out debris in the well
- The seepage area gas has declined to no measurable flow at this time. The area continues to be monitored
#1621: Royalite (Dingman) #2 Operations Update August 11, 2009
Submitted by Barb on Wed, 08/12/2009 - 09:56. For Visitors- Operatons are being continued to remove the drill pipe and prepare the well for installing casing.
- The seepage area gas has declined to no measurable flow at this time. The area continues to be monitored.
#1620: Royalite (Dingman) #2 operations Update August 10, 2009
Submitted by Barb on Wed, 08/12/2009 - 09:52. For Visitors- The drill bit is at a depth of 543 meters. The suspecte old casing has been drilled through.
- Preparations are being made to remove the drill pipe and prepare the well for installing casing.